City of Concord Electric Systems crews power down the electric vault on Barbrick Ave.
City of Concord Electric Systems crews worked through the night on February 13 to power down the electric vault on Barbrick Ave and remove the equipment inside that provided electricity to our streetlights and tree lighting on Union St. Demolition continued today to remove the vault and make way for the new 42 inch storm drainage pipes that will be installed as part of the Downtown Concord Streetscape project.
New temporary solar lighting was installed a few weeks prior to light Union St. while the streetscape project is underway.