Construction Updates

September 22, 2023 Streetscape Update

This week, Streetscape crews worked on installing the 30in stormwater drainage pipes on Union St. between Barbrick Ave. and the midblock. Next, they will install the 15 in. drainage pipes on Union St. between Barbrick Ave. and Corban Ave. before moving on to grading work and installing the new curbline!

Stormwater Structure
Stormwater Structure in Progress
30″ Storm Drainage Pipe Installation
Curb Inlet Buildout
Stormwater Structures in Progress

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC