October 6, 2023 Streetscape Update

Our Downtown Streetscape crews have nearly completed the water line and storm water drainage pipe work within the current work zone! Next week they will finish the 15″ storm drain installation you see in the photos below. They’ve also been setting the new curb inlets. Check out the new storm drains installed this week on Union St!

Come Downtown and checkout the progress! Stay up to date with the Downtown Streetscape Project and what’s happening in Downtown Concord follow us on Facebook and Instagram!

Teporary Removal of Dirt for Storm Drain Installation
Start up of 15-inch RCP Installation
Demolition of old waterline
15-inch RCP Installation
15-inch RCP Installation
Double Curb Inlet Installed
General Cleanup of Site