Downtown Streetscape Crews have been fortunate this year with good weather however, this week that was not the case. Up until this point, most of the rain Concord experienced this year was on the weekends and not through the full week so it hasn’t impacted construction.
What does this mean for the Streetscape Project? Crews will have to wait until the rain passes to get started on the work described in last week’s post. They plan to work Friday and Saturday on prep work for installation of the new water services starting next week.
To stay up to date with the Streetscape Project and what’s happening in Downtown Concord follow us on Facebook,Instagram, and Twitter!