July 26, 2024 Streetscape Update

This week, Streetscape crews installed conduit at Cabarrus Avenue and started rough grading the intersection. Meanwhile, infrastructure crews removed the roadway north of Cabarrus towards the Library and began the new sewer main installation. During the roadway removal, old trolley tracks were discovered just 2 ft. below the asphalt on Union Street! While most of what was uncovered wasn’t in great shape, we were able to preserve what we could and relocate them for safekeeping.

South of Cabarrus Avenue sidewalk crews worked hard installing formwork and pouring new sidewalks.

Weather permitting, next week, crews will continue pouring the sidewalk on the east side of Union up to Cabarrus Avenue and start installing brick pavers as infrastructure crews continue working on the new sewer.

To stay up to date on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Trolley Tracks found north of Cabarrus Avenue
Light Pole Base Installation
Conduit Installation at Cabarrus Avenue
Conduit Installation at Cabarrus Ave
Conduit Installation at Cabarrus Avenue
Flowable fill for Conduit Installation
Sidewalk pour on the east side of Union St S

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC