July 19, 2024 Streetscape Update

Downtown Streetscape crews continue to make progress in the Cabarrus Avenue intersection. Currently, they are installing stormwater across the intersection working north. We anticipate crews to complete this work by early next week then they will switch to sewer work at the intersection and work north towards the library. At this point, some fence movement will occur to keep crews and pedestrians safe.

With the stormwater complete grading crews will start building back the roadway at the intersection.

Multiple crews continue working on sidewalks including installing soil cells, light pole bases, formwork, and new concrete sidewalk pours. Additionally, we’ll see brick paver crews return to install pavers on the east side of Union Street.

To stay up to date on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Form for Retaining Wall
Form for Heavy Duty Sidewalk Pour
New Sidewalk and Retaining Wall at 57 Union St S
Sonnet Tube for Light Pole Base
8″ Roof Drain at 21 Union St S
4″ Meter Vault Grade Adjustment
Stormwater Structure
Existing Utilities at Cabarrus Ave
Fire Hydrant installation at 4 Union St N

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC