Skip to main content

Construction Updates

January 24, 2025 Streetscape Update

This week, crews milled and paved the final asphalt for the Streetscape Project between Corban and Foard Avenue. They also installed temporary road striping in this area. Final thermoplastic road striping will be installed when the temperatures warm up in the Spring.

Prep work for the ADA curb ramps at the corner of Union St and Corban Ave near Rotary Square is finished and concrete will be poured today.

Electric crews also continued to pull wire for the light poles, receptacles, and tree uplighting throughout the work zone, and traffic signs are being installed.

Next week, wire pulling will continue, stamped asphalt for crosswalks will begin, and crews will continue pressure washing and cleaning the site.

Tack at Union St and Corban Ave
Paving Corban Ave
Paving Union St and Corban Ave
Union Street S Paving
Prep for ADA ramp at Rotary Square
Survey Stone Plaque Reinstalled

Stay informed

Get the latest information about the revitalization of Concord Downtown.

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC