This week, Streetscape Crews continued installing soil cells south of Barbrick Ave. They also continued installing new 2″ water services north of the Midblock Crosswalk.
In between the Midblock Crosswalk and Barbrick Ave crews worked on grading and installing form work for new concrete to be poured early next week. We anticipate installation of soil cells, water services, and sidewalk work to continue through next week.
There is always a lot happening in Downtown! Check the Events & Promotions page to see what’s going on this weekend.