Construction Updates

December 15, 2023 Streetscape Update

This week, Downtown Streetscape crews started pouring a base layer of asphalt on Union Street from the Midblock to Corban Avenue. They also installed ADA ramps on sidewalks along Barbrick Avenue and Market Street. Getting the first layer of pavement down prior to the expected rain over the weekend helps protect the stonework.

Next week, crews will continue working misc. concrete work as well as work on the Courthouse Plaza connection on Union Street and, weather permitting, complete the base layer asphalt on Union Street and Barbrick Avenue.

Stay up to date with the Downtown Streetscape Project and what’s happening in Downtown Concord follow us on Facebook, Instagram, and X (Twitter)!

Paving on Union Street
Paving on Union Street
Paving on Union Street
Concrete Blankets to protect from Low Temps
New ADA ramp at Barbrick Ave and Market St
New ADA ramp at Barbick Ave and Spring St

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC