Construction Updates

August 9, 2024 Streetscape Update

This week, Streetscape crews made progress on the new 16″ water main installation, north of Cabarrus Ave towards the Library.

At the Cabarrus Ave intersection, the first layer of asphalt has been poured and grading/formwork for the curbs is installed.

On the east side of Union Street between the mid-block and Cabarrus crews installed brick pavers. On the west side, crews installed formwork and performed grading for new sidewalks.

Tropical Storm Debby slowed things down yesterday, but crews are back out working hard today!

To stay updated on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Cabarrus Avenue curb formwork
Storm water inlets on Cabarrus Ave
Signal Pole conduit installation
Water line installation
Water line installation
Sidewalk formwork installed
Sidewalk formwork installed
Brick Paver installation in progress
New Brick Pavers

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC