August 2, 2024 Streetscape Update

Come downtown and check out the progress while enjoying a beverage in our new Downtown Concord Social District! 🍻

This week, south of Cabarrus Avenue, sidewalk crews were hard at work installing more sidewalks, retaining walls, and seat walls on the east side of Union St. They also installed light bases and started grading for new curbs.

Grading continued through the Cabarrus Avenue intersection and the first 5″ asphalt pour is scheduled today.

North of Cabarrus Avenue infrastructure crews installed the new sewer main and are scheduled to complete the lateral connections today. Next week, infrastructure crews will continue working on the water line starting at Cabarrus and moving north toward the Library. There may be some additional fence movement but Library access will be open.

To stay up to date on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Cabarrus Intersection
Grading Cabarrus Intersection
Formwork for reinforced Sidewalks and Retaining Wall
Seat Wall Installation
Sidewalk pour on east side of Union Street
New Sidewalk and Seat Wall
Start of paving asphalt base for Cabarrus Avenue Intersection
Sewer lateral connection

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC