August 16, 2024 Streetscape Update

This week, Downtown Streetscape crews completed the 16″ water main installation up to the Library. They also pressure-tested the new water line and started installing water services. Water service installation will continue the next few weeks.

Curbs and the second layer of asphalt were poured at the Cabarrus Avenue intersection in preparation for the intersection opening to through traffic Friday evening!

Brick paver installation, formwork, and grading of sidewalks continued south of Cabarrus Avenue. Roadway crews also began installing stone on Union Street from the midblock towards Cabarrus Avenue. Following stone installation crews will pour curbs between the midblock and Cabarrus.

To stay updated on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Excavation on Union St N
Formwork for Curb at Cabarrus Intersection
Formwork for Curb at Cabarrus Intersection
Formwork for Curb at Cabarrus Intersection
Formwork for Curb at Cabarrus Intersection
Form sidewalk west side of Union St S
New curb at Cabarrus Ave
New curb at Cabarrus Ave
New curb at Cabarrus Ave

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC