Work continues on the Union Streetscape as crews grade, form, and pour concrete for the new sidewalks, and install brick pavers and granite restraint edges.
North of the Midblock Infrastructure crews are working hard on the new 12″ sewer line installation with approximately 100 of the 285 feet installed.
We’ve had great weather this week and a lot of progress was made! Come see it for yourself this weekend and support local! Check out our Business Directory and Events and Promotions Page.
Concrete Pour at the corner of Barbrick Ave and Union St
Grading at the Corban Ave Intersection
Driveway Access to Business near Corban Ave
Landscape Edge installation
Sidewalk work in front of 2 Gals Kitchen
New wide sidewalks on Union St!
Courthouse Plaza connection on west side of Union St