This week, Streetscape crews completed concrete pours and installed brick pavers at the Midblock Crosswalk. They also installed light pole foundations and future public art foundations.
Infrastructure crews completed the 4″ water meter vault north of Cabarrus Avenue. With the vault installed, the water line work up to the Library is complete. Next, crews will begin stormwater installation within the work zone.
Heads up! The next (and final) fence shift is tentatively scheduled for September 16th up to Killarney Ave.
Come Downtown and check out the progress on Union Street for Art Walk on Saturday, September 7th from 11 AM – 4 PM!