Construction Updates

August 23, 2024 Streetscape Update

This week on Union Street, infrastructure crews completed three 2″ water services in their current work zone between Cabarrus Avenue and the Library.

Sidewalk crews poured 250 ft of sidewalk and 275 LF of landscape edge on the west side of Union Street South and started installing brick pavers. They also installed 500 LF of the curb between the midblock and Cabarrus Avenue on both sides. Now that the curb is in place crews will continue work on the roadway pouring asphalt next week and sidewalk crews will continue concrete and brick paver installation.

To stay updated on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

Temporary crosswalk at Cabarrus Avenue
Cabarrus Avenue open to traffice
Cabarrus Avenue Intersection
Installing stormwater feature with Granite Curbs
Water service installation
Reinforcement for concrete pour at Cabarrus Ave
Stone installation for curb subgrade
Formwork for Sidewalk west side of Union St
New Sidewalk Install
New Sidewalk Install
Curb installation on Union St S

 

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC