Construction Updates

June 14, 2024 Streetscape Update

This week, Downtown Streetscape crews completed the conduit installation between Corban Ave and Cabarrus Ave. They also installed a line-stop to isolate the water in the Cabarrus Ave intersection so crews can begin removing existing water lines and installing the new lines.

Our City Electric Systems crews installed temporary lighting to keep the Cabarrus Ave intersection well-lit during construction.

Next week, crews will continue working on the landscape drains and pouring sidewalks between the Midblock and Cabarrus Ave. They will also work in the Cabarrus Ave intersection installing the new 16″ water line.

Are you heading Downtown this weekend? Be sure to check out our Parking Map for the latest information. Both Parking Decks remain open with ample free parking all weekend long!

To stay up to date on the Downtown Streetscape Project follow us on Facebook, Instagram, and X (Twitter)!

 

Form for New Sidewalks
Excavation for new Landscape Drain Lines
Existing Lateral Sewer Service to be Reconnected
16-in. Line Stop and new 16-in. Valve
16-in. Line Stop
Conduit Installation up to Cabarrus Ave.
Temporary Lighting by City Electric

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC