Downtown Streetscape crews continued work on water services, sewer services, electrical and fiber conduit, landscape edging, and sidewalk grading this week.
The electrical contractor also started work on the foundations of the new festoon light poles near the Courthouse Plaza and sidewalk crews started working on foundations for the new seat walls that will be near the Corban Ave intersection.
Staff presented a progress update to City Council last night. A recording of this presentation can be views on YouTube (starts at 19:22).