Construction Updates

March 8, 2024 Streetscape Update

Despite one rain day, our Downtown Streetscape crews have been hard at work this week!

They’ve installed electrical conduit near the courthouse plaza and continued installing the 2 inch water services to businesses between Cabarrus Ave and the Midblock Crosswalk. Sidewalk crews are also continuing to grade and install the sidewalks on Union St, south of Barbrick Ave and are working on framework for the new landscaping bed edges between Barbrick Ave and the Midblock Crosswalk.

There is always a lot happening in Downtown! Check the Events & Promotions page to see what’s going on this weekend.

And stay up to date with the Downtown Streetscape Project by following us on Facebook, Instagram, and X (Twitter)!

New conduit installed
New 6″ waterline to serve 30 Union St S
New tree grate frame installation
New pipe for fire hydrant assembly
Formwork for landscaping edge

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC