Construction continues on Union Street with multiple Streetscape Crews on site.
This week, the Electrical Contractors were out installing conduit and pull boxes near the Courthouse Plaza. Waterline Crews continued with 2″ water service installation north of the Midblock Crosswalk. And sidewalk crews continued grading and started installing tree grates to prepare for concrete pours south of Barbrick Avenue.
Weather permitting, similar work will continue next week with water service installation north of the Midblock Crosswalk, conduit work towards Cabarrus Ave, and sidewalk work south of Barbrick Ave.