This week, Downtown Streetscape crews finished installing the section of water line from the Midblock to Cabarrus Ave. Since then they’ve begun pressure testing the line and plan to start installing water services next week.
Crews also installed fiber and electric conduit on Union St. from Barbrick Ave. to Corban Ave. And they plan to continue concrete work at the corner of 66 Union St. S next week.