This week, Downtown Streetscape crews completed undercutting the roadway, installed stone, and finished installing most of the curbs along Union Street and Barbrick Avenue. Tomorrow, crews will bring in 8″ of stone to cover the surface of the road from curb to curb in preparation of asphalt that’s soon to follow!
During the hustle and bustle of the holiday season, don’t forget to shop small and support our Downtown merchants!
And check out our events page for all the things happening Downtown this weekend!
Stay up to date with the Downtown Streetscape Project and what’s happening in Downtown Concord follow us on Facebook,Instagram, and X (Twitter)!
Compacting subgrade on Union Street
Curb Installation on Union Street
Curb Installation on Union Street
Curb Machine
Double Curb Inlet on Union Street
Demolition in preparation of new ADA curb inlet on Barbrick Avenue
Geo-Fabric subgrade on Babrick Avenue
Curb Installation on Barbrick Avenue