Construction Updates

March 20, 2023 Streetscape Update

This week’s Streetscape update! You’ve heard us talk about the water lines crews have been working on, so today we’re going to give you an up-close glance at the underground progress.

✔ The new 16″ main water line was installed between Corban Ave. and Barbrick Ave.

✔ Two new fire hydrant services were installed between Corban Ave. and Barbrick Ave.

✔ This week (March 20-24) crews are working to install the new 16″ main water line from Barbrick Ave. to the Midblock between Cabarrus Ave. and Corban Ave.

⭕ Coming up next, crews will begin installing water services to all the local businesses within the construction zone.

This main water line and water service installation is expected to take around two months.

After water services have been installed, crews will move on to storm drainage work within the current work zone.

New Water Line Installation on Union St S
16×6 Tee and valve for FHA and Service 57 Union St S
16×6 Tee for fire line at 52 Union St S
New FHA at Barbrick Ave on existing Main Water Line
New Fire Hydrant Leg on Barbrick Ave
Tap for new FHA on Barbrick Ave
2 inch Service for 66 Union St S
2 inch Service with PRB for 66 Union St S

Stay informed

Get the latest information about the revitalization of Concord Downtown.


© All rights reserved. Design by Perry Productions

Concord Downtown 704-920-6130
30 Cabarrus Avenue W 28026 Concord, NC