This week, Downtown Streetscape Crews continued valve insertions on Union St N near Killarney Ave to isolate the existing water lines before installing the new 16″ water line through Cabarrus Ave.
Sidewalk Crews continued grading and installing formwork for upcoming sidewalk pours. This will continue through next week with concrete pours planned for the following week.
Are you heading Downtown this weekend? Be sure to check out our Parking Map for the latest information. Both Parking Decks remain open with ample free parking all weekend long!
Foundation Core for new Signal Pole at Union St & Cabarrus Ave
New 8-inch Valve at Killarney Ave & Union St (Night Work)
Reinforced Deadman Blocking on 8-inch water lin