April 5, 2024 Streetscape Update
April 5, 2024
The Downtown Streetscape crews continue to pour sidewalks, install light bases near Barbrick Ave, and install soil cells, bollards, and seat walls on Union Street. Today, crews will finish connecting the last 2″ water service line within the current work zone to the main water line. As infrastructure work continues on Union St. between Cabarrus […]